My wife had asked me last fall if I would construct another flowerbed for her on one side of the driveway, and of course I said "sure, i'll start on it next spring." So, the time has arrived for constructing the very big flowerbed that will have small trees, shrubs, and of course flowers in it later. This is gonna be a really big flowerbed, measuring 5 feet wide and 28 feet long. Landscaping timbers are the material of choice, and i'm gonna show you how to build it on a severely unlevel landscape.
Photo below - here's the area that was presented to me. It was completely engulfed in honeysuckle vines, small saplings, weeds of all kinds, and was cleared off a couple of weeks ago. Once relatively cleaned up, the entire area was sprayed with Roundup brush killer, so that no new growth would form over the next few weeks. As you can see in the photo, it is high in the middle, and also has a little dip that recedes into the crushed stone in the driveway.
Here's a video that explains how to lay out the area so that the box will be square.....
Photo below - after laying out the area with twine as seen in the video, begin at the lowest spot of elevation with timbers. Since the area is sloped pretty bad, a shallow trench was dug along the string which loosens the earth a bit, and also provides a base for the timbers to reside. The trench itself is only 2-3", for reference. After laying a 4 ft. level on top of an 8 ft timber laid in place, it clearly showed that the slope was pretty severe. Rather than dig a deep trench long enough to lay the entire timber in, I always opt for a much shorter starter piece. This is always done in 2 foot increments, and the one in the photo was cut to a length of 4 foot. Still out of level pretty bad, the amount of trenching needed to make level has been greatly reduced by going with a shorter piece.
Photo below - here's a good picture of the shallow trench that was dug along the string.
Photo below - once the 4 ft length of timber has been leveled along the long side, the short side should be leveled as well by putting a torpedo level on top, and adjusting the earth below as needed. This is where a 4 lb. hammer really comes in handy, as I just beat the crap out of the timber (ok, not really - but you get the idea) to get it level. :-)
Photo below - once completely level, a 6 foot piece is laid on top to create a stair-step effect. At 3" thick each on the timbers, this method has already reduced trenching on the left side by a total of 6". I don't know about you, but digging is for the birds, and i'd rather not do anymore than I have to! Blech!
Photo below - the remaining 4 foot piece that was leftover from the first piece cut is laid on top to gain even more elevation. Doing it this way gives it a uniform look, which gives a really good indication that lots of planning and detail went into it. Besides - everyone driving by in a car will see it, so it needs to look as good as possible (unlike some that I see while driving through town - sheesh!)
Photo below - an 8 ft piece is butted against that, and now we're getting somewhere.
Photo below - Using two levels, this new addition is checked again to see if any adjustments need to be made. The open areas underneath the stair-stepped timbers should be of no concern, because they have no effect on the rigidity of the construction, and will be backfilled with gravel and soil later. Nobody will ever know the difference in the end.
Photo below - to keep the timbers level on the short side, I simply wedge rocks underneath to keep them true. Hammered into place gently, they provide support while everything is put into place.
Photo below - timbers are stacked until the entire length is completely level on top, and in this case required 5 timbers at the lowest end. A depth of 15" of digging along most of the length was averted by doing it this way. Now to anchor these pieces into place with some 3/8" rebar.....
However, before that can be started I need to spend some time with Jude. Of course by presenting her frisbee to me like this, there's no way I could ignore her. I needed a break anyway, because it's really hot outside, and the towel used to wipe sweat away is drenched!
Photo below - Now that Jude has been appeased for a little while, it's time to begin anchoring the timbers into place. I do it with pieces of 3/8" rebar purchased from Lowes - which requires a 4 lb. sledgehammer, cordless drill, and a really long 3/8" butterfly drill bit. After lining the ends of the timbers up, simply bore through them, then drive the rebar through - and into the earth below. This is probably my least favorite part of constructing a box this way, because it's pretty tough going - as you can imagine.
Take care, and happy building!
EG
4 comments:
Very cool, EG. I love watching you do things on a slope. It looks great.
Looks like it will last. You do build solid stuff. Thanks for the post.
ribbit - thanks, i'm glad you like it! Everything I build is on a slope, so it's just "life".
Gardener - Thanks. I try my best to make everything really durable.
Look very nice EG. It will really spruce up your front yard. The only thing I am building this year is an 8x10 deck at the back door. Possibly a fence to keep the neighbors from running into my stuff too!
Post a Comment